Payment Schedule
| 1. Additions | Back to Top |
|---|
| Deposit | 15% |
| Start of Framing | 25% |
| Start of Electrical | 25% |
| Start of Drywall | 25% |
| Completion | 10% |
| 2. Basements/Recrooms | Back to Top |
|---|
| Deposit | 15% |
| Start of Insulation | 35% |
| Start of Drywall | 40% |
| Completion | 10% |
| 3. Bathrooms | Back to Top |
|---|
| Deposit | 15% |
| Start of Plumbing R.I. | 25% |
| Start of Drywall | 25% |
| Start of Fixture Installation | 25% |
| Completion | 10% |
| 4. Domers/Second Story | Back to Top |
|---|
| Deposit | 15% |
| Start of Framing | 25% |
| Start of Electrical | 25% |
| Start of Drywall | 25% |
| Completion | 10% |
| 5. Garages/Carports | Back to Top |
|---|
| Deposit | 15% |
| Start of Framing | 25% |
| Start of Roofing | 25% |
| Start of Parking Pad | 25% |
| Completion | 10% |
| 6. Kitchens | Back to Top |
|---|
| Deposit | 15% |
| On Cabinet Order | 25% |
| Start of Plumbing R.I. | 25% |
| Start of Cabinet Installation | 25% |
| Completion | 10% |
| 7. General Contracts Less Than $1500.00 | Back to Top |
|---|
| Deposit | 15% |
| Start of Installation | 50% |
| Completion | 35% |
| 8. Leasehold Improvements | Back to Top |
|---|
| Deposit | 15% |
| Start of Framing | 25% |
| Start of Electrical | 25% |
| Start of Drywall | 25% |
| Completion | 10% |
|
|
|
|
|
|